TM 11-6625-291-14/TO 33A1-7-23-1
2-6. INITIAL ADJUSTMENTS.
The initial adjustments in this section are listed below.
Meter needle zero adjustment for TS-585AU
Meter needle zero adjustment for TS-585B/U, TS-585C/U, or TS-585D/U
2-7. METER NEEDLE ZERO ADJUSTMENT FOR TS-585A/U.
This task covers:
Adjustment
INITIAL SETUP
Tools
Personnel Required
TooI Kit, Electronic Equipment
One operator
TK-105/G
Materials/Parts
Equipment Condition
None
Output meter on workbench
ACTION
REMARKS
ITEM
LOCATION
ADJUSTMENT
NOTE
Look at meter needle from directly above. If meter needle Is not
directly above zero marking, perform the initial adjustment.
Using flat-tip screwdriver, turn screw left
Zero-set
Output Meter
or right to aline meter needle with zero
adjustment screw (1)
TS-585A/U
mark.
and meter needle (2)
2-12