2-5. UNPACKING PROCEDURE.
This task covers:
Unpacking
INITIAL SETUP
Personnel Required
Tools
Tool Kit, Electronic Equipment
One operator
TK-105/G
Materials/Parts
Equipment Condition
Output meter on workbench
None
ACTION
REMARKS
ITEM
LOCATION
REMOVAL
1 . Waterproof
Using pocket knife, cut seam along cover of
Cover flaps (1)
waterproof carton. Fold back cover flaps.
carton
Remove.
Waterproof
2.
Waterproof envelopes contain output
envelopes (2)
meter manuals.
Remove.
Corrugated tray (3)
3.
Remove.
4.
Inner carton (4)
Remove.
Output meter (5)
5.
NOTE
Check the basic issue items list is appendix C for all items
needed for the operation of the output meter.
2-10